General repair of eight cells of the forced draft CT No. 2

Datum: 19.7.2017

General repair of eight cells of the forced draft CT No. 2

Complete repair of eight cells containing fans with a diameter of 8m. The works performed included demolition of the existing reinforced concrete diffusers, disassembly of the existing asbestos cement, shelling and water supply piping. Restoration of reinforced concrete structures, assembly of the new coating Solux, water supply piping and reinforced concrete diffusers.
Customer: Duslo, a.s.
Place of realization: Šala, SK
Start date: 2008
Completion date: 2008